Haryana Chief Minister Orders Fresh Tender and Inquiry into Gurugram Sewage Treatment Plant Delay
Hry CM orders fresh tender, probe into 6-yr delay in Gurugram STP
Hindustan Times
Image: Hindustan Times
Haryana Chief Minister Nayab Singh Saini has directed the Gurugram Metropolitan Development Authority to reissue a tender for a 100 MLD sewage treatment plant in Dhanwapur after a six-year delay. The project, initially approved in 2020, faced high bids, leading to its cancellation and a new payment framework.
- 01Chief Minister Nayab Singh Saini has ordered a fresh tender for a sewage treatment plant in Gurugram.
- 02The project has faced a six-year delay since its approval in 2020.
- 03Initial tender bids were excessively high, prompting a cancellation.
- 04A new payment structure will provide 51% payment upon completion and the rest after a 10-year maintenance period.
- 05An inquiry will determine accountability for the delays.
Advertisement
In-Article Ad
Haryana Chief Minister Nayab Singh Saini has mandated the Gurugram Metropolitan Development Authority (GMDA) to reissue a tender for the construction of a 100 MLD sewage treatment plant (STP) in Dhanwapur, following a six-year delay since its approval in 2020. The original tender for the ₹166 crore (approximately $20 million USD) project was canceled due to excessively high bids from three bidders. Under the new framework, the contracting company will receive 51% of the payment upon completion of the STP, with the remaining 49% disbursed after a 10-year maintenance period. The chief minister expressed concern over the delays and ordered an inquiry to assign responsibility. Additionally, the meeting approved a 665 MLD main pumping station at Dhanwapur for ₹101 crore (approximately $12 million USD) and a proposal for a consultant for a new drain from Gurugram to Palwal.
Advertisement
In-Article Ad
The reissuance of the tender and the construction of the sewage treatment plant will improve sewage management in Gurugram, potentially reducing environmental issues and enhancing public health.
Advertisement
In-Article Ad
Reader Poll
Do you believe the government is doing enough to improve sewage management in Gurugram?
Connecting to poll...
More about Gurugram Metropolitan Development Authority

Gurugram Metropolitan Development Authority Announces ₹21 Crore Revamp of Sheetla Mata Road
Hindustan Times • Apr 7, 2026

NHAI Raises Safety Concerns Over Pipeline Work on Dwarka Expressway
Hindustan Times • Apr 4, 2026

Gurugram Authorities to Invest ₹370 Crore in Badshahpur Drain Concretisation
Hindustan Times • Apr 4, 2026
Read the original article
Visit the source for the complete story.